I must confess that at 8 meters drop, we are working close to the limit of the “Twister” style design. Why?…Well as the crystal chains get longer, they get heavier. And eventually the weight of the glass will cause the clips to open up, which is no good at all.

We can work around this by using heavier weight clips, and glass with 10% lead content, which is considerably lighter than 20% and 25% lead crystal. The photos you see below, show the installation sequence that took 2 days. 
Preparing the anchor point
1 Preparing the anchor point
Lifting the frame into place
2 Lifting the frame into place
Working on the top cylinder
3 Working on the top cylinder
Top half complete, starting to dress the bottom strands
4 Top half complete, starting to dress the bottom strands
Close up
5 Close up
Lower half starting to take shape
6 Lower half starting to take shape
Finished looking down
7 Finished looking down
Job done!
8 Job done!